Answer:
a. the buyer’s consumer surplus for that good is maximized.
Explanation:
The consumer will purchase up to the moment at whose preference price matches the market price.
Because of the diminished return theory, the following unit (k+1) will have a lower benefit to the consumer thus, it will have purchased only if the price is lower. Therefore, it will not purchase as the market price is the same as the previous unit but the consumer benefit is lower.
Answer: B. Shampoo and conditioner, with an elasticity of -3.5.
Explanation:
Complimentary products are those which see their quantity demanded move together because the goods usually compliment each other like tea and sugar.
Their Cross-price elasticity shows this by being a negative figure. This is because when the price of one commodity goes up, the quantity demanded of the other goes down because higher prices lead to lower quantity demanded.
The actual question showed that Conditioner and Shampoo had a cross-price elasticity of -3.5 so this is the correct answer.
An Activity-based system uses numerous overhead cost pools.
<h3>What is activity-based costing?</h3>
Activity based costing is a method of costing that is used in accounting to apportion costs to a good or service produced. It believes that manufacturing requires the use of resources which require activities and so these activities can be given costs.
To give these activities costs, there is a need to use overhead cost pools which is why activity-based systems use several overhead cost pools.
Find out more on activity-based costing at brainly.com/question/6654166
#SPJ1
Increase its visibility in search results on search engines
Answer:
d. It determines the critical path for the completion of a series of interrelated activities.
Explanation:
The Critical Path method is a method to lay out the different steps or interrelated activities of a project, in a graphical manner, that shows the interrelations, the time each activity takes to complete, the different alternatives or paths for project completion, and the total completion time for the project.
It also shows the amount of time a delay in one of the activities would delay the project as a whole.