Answer:
- <u>std rate $30.64</u>
- <u>efficiency variance $6,128.00</u>
Explanation:
We will work the rate variance to obtain the standard rate:

actual rate $29.20
actual hours 11,700
difference $1.44
rate variance $16,800.00

<u>std rate $30.64</u>
<u></u>
<u>Now we can solve for the labor efficiency variance:</u>
std hours 11700
actual hours 11500
std rate $30.64
difference 200
<u>efficiency variance $6,128.00</u>
The diference is positive, sothe variance is favorable.
Based on microeconomic theory, <u>Total</u> costs refer to the sum of the fixed and variable costs for any given level of production.
<h3>What makes Total Cost?</h3>
Generally, the total cost is the sum of all the price of the material utilized, the wages or salary paid in the production, and the direct expenditure.
<h3>Components of Total Cost </h3>
The components of Total Cost include the following:
- Prime cost
- Factory cost
- Office cost
- Cost of sales, etc.
Hence, in this case, it is concluded that the correct answer is "<u>Total Cost."</u>
Learn more about Total Cost here: brainly.com/question/25109150
Based on the various activities for the month that were reflected in your checkbook, your new balance would be $135.84.
<h3>What is the checkbook balance?</h3>
This can be found as:
= Opening balance + Deposits - Checks and withdrawals
Solving gives:
= 134.56 + 345.12 - 32.19 - 250 - 16.65 - 45
= $135.84
In conclusion, your new balance is $135.84.
Find out more on checkbook balances at brainly.com/question/3719189
#SPJ1
Answer:
$1,049
Explanation:
Data given in the question
Par value = $1,000
Interest rate = 4.9%
Time period = 10 years
So, by considering the above information, the price paid to the bond holder is
= Par value + Par value × rate of interest
= $1,000 + $1,000 × 4.9%
= $1,000 + $49
= $1,049
Hence. the price paid to the bond holder is $1,049