Answer:
Explanation:
Overhead allocated to Product X = Department A overhead cost+ Department B overhead cost
= $51,157.84+$5755.62=
= $56,913
Calculations:
Using a single-driver allocation system, with direct labor hours as the driver, how much overhead was allocated to Product X:
Department A's Overhead rate per labor hour = Overhead costs/Total direct labor hours = $4300000/60000 hours = $71.66 per hour
Overhead (Department A) = $71.66per hour*724 labor hours
= $51,157.84
Department B's Overhead rate per labor hour = Overhead costs/Total direct labor hours = $2200000/60000 hours = $36.66 per hour
Overhead (Department A) = $36.66 per hour*157 labor hours
= $5755.62
Answer:
The change will impact all 300 locations. The letter should be written to entire staff of the SpaceX.
Explanation:
To: All Staff SpaceX Team
Subject: Change over details (First Launch)
As you all are already aware about the implementation of new software named First Launch . The software installation run will start from March 1, 2021 at 9:00 a.m. Every accountant receiving the new product will require to install the software within 48 hours. Failure to do will result in expiry of the password which will require resending the software. After installation all accountants must restart the computer.
This change will affect all 300 locations across the United States. The changeover will result in improved efficiency, increase in security and there will be more transparency.
If there is any concern or query regarding this change feel free to write the team implementing the change.
Regards,
Director Accounts.
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.