The cycle time of this process for the firm is 2.89.
<h3>What is a Cycle Time?</h3>
This refers to the average time between the start of production of one unit and the start of production of the next unit of production
Cycle Time = Net time available to work / Customer demand
Cycle Time = 1.1 + 1.5 / 0.9
Cycle Time = 2.88888888889
Cycle Time = 2.89.
Therefore, the cycle time of this process for the firm is 2.89.
Read more about cycle time
<em>brainly.com/question/18802868</em>
#SPJ1
<span>we will explore the recruiting process used by human resource managers to review applications, test and interview candidates, perform reference checks and request health checks.The hiring process is the process of reviewing applications, selecting the right candidates to interview, testing candidates, choosing between candidates to make the hiring decision and performing various pre-employment tests and checks</span>
Answer:
$35,000 is the maximum amount that Crigui should pay
Explanation:
Total cost if manufactured internally;
Direct materials $13,000
Direct labor 15,000
Variable overhead 3,000
Fixed overhead 7,000
————
Total cost $38,000
Therefore, $38,000 - $3,000 (unavoidable cost) = $35,000
No, you should not.
Explanation:
It’s illegal for employers to ask for that data.
Answer:
Identify the sequence of tasks that take the longest to complete
Explanation:
Program Evaluation and Review Technique (PERT) is a project management tool that is used to manage potential contingencies in the process of executing a project. It is used to schedule ,organize and coordinate tasks in a project.
Determining the critical path on a PERT network lists out the time required for different tasks to be completed and as a result , the sequence of tasks that require the longest time are identified.