The answer to the question is d
9514 1404 393
Answer:
8
Step-by-step explanation:
The number of days has gone down by a factor of 15/24. The number of workers is inversely proportional, so must increase by a factor of 24/15 = 8/5.
(5 workers) × (8/5) = 8 workers
8 workers are needed to complete the project in 15 days.
If the question is supposed to be
Now multiply both sides by 3 to get 3(-21)=-63=e
32 x4 = 128 ft
128 x 12 = 1536
Final Answer: 1,536 inches