Answer:
Is better to continue the production of the component as currently is taking allocated overhead from other department. Buying will inccur in a financial disadvangate of 25,000
Explanation:
<u>Make</u>
Direct cost:
DM 120,000
DL 25,000
VMO <u> 45,000 </u>
Total Variable: 185,000
Tracable fixed cost: 5,000
Total cost: 190,000
<u>Buy option:</u>
purchase 190,000
unavoidable cost: (30,000 - 5,000) = 25,000
Total cost: 215,000
Answer:
The correct answer is: shortage; elastic; same number of.
Explanation:
Suppose the price ceiling is fixed at $50. The market equilibrium price is more than $50. This means that the price ceiling is binding.
Fixing the price ceiling below the equilibrium price level will create a shortage of tickets. There is an inverse relationship between price and quantity demanded. So the quantity demanded will be higher at a lower price. The quantity supplied on the other hand will be lower. This is because the quantity supplied is positively related to the price.
So at the ceiling price the quantity demanded will be higher than the quantity supplied. This shortage will be more if the demand is elastic. An elastic demand implies that a decrease in price will cause the quantity demanded to increase to a greater extent.
Answer:
True
Explanation:
Critical-Chain
This was introduced or originated by Eli Goldratt in 1997. Its aim is to challenges conventional project management approaches and absolute dependence on TOC principles. The idea of what to change or eliminated is the largely rooted behaviors that is common with the traditional project management practices. It is very multitasking anf it is the longest string of reliance that occur on the project.
Critical- Chain Approach
This approach simply covers project network as it ca be limited by both resource and technical reliance/dependencies. each type of limitations can create task reliance.
The Summary of Critical Chain Approach
1.) use Aggressive but Possible Times (ABPT) for task durations
2.) identify the critical chain by accounting for resource dependencies
3.) use buffer management to track project progress etc.
The new price level after the increase in the money supply is 3.3. Therefore, the percentage increase in the money supply is 10%. The percentage change in the price level is 10%. Percentage change in the money supply is the same as the percentage change in the price level.
Answer:
budgeted costs for direct materials
budgeted direct manufacturing labor
budgeted manufacturing overhead
Explanation:
Direct materials costs are $4.00 per pool cue.
Direct manufacturing labor is $6.00 per pool cue.
Manufacturing overhead is $0.84 per pool cue.
total budgeted direct materials = 22,000 x $4 = $88,000
total budgeted direct labor = 22,000 x $6 = $132,000
total budgeted manufacturing overhead = 22,000 x $0.84 = $18,480
The information about the beginning and ending inventories is not relevant to this question since it only deals with budgeted or estimated costs which may or may not differ from actual costs.