Answer:1. $7720
2. $7945
3. $7758
Explanation: 1. First in First out method which means the first inventory to be purchased by company will be the first to be sold.
Total cost of Sales = Total number of units Sold * Total Cost of inventory sold
= 100units*$5+ 300units*$5.30+ 200units*$5.35 + 450units*$5.60
=$7720
Total units sold=1450 we started from first inventory which was the balance of inventory of 100 units downwards up to the 1450th unit sold that was purchased on the 26th of April by the company.
2. Last in first out method is where the last bought inventory is sold first.
Total cost of sales= Total number of units sold * Total cost of units sold =200units$*5.80+ 600units*$5.60+ 200units*$5.35+300units*$5.30+150units*$5.1
=$7945
Total units sold still 1450 but we calculated the cost from the last purchased unit from 30th April to the 1450th unit sold which was on the 12th of April.
3. Average Cost = (Sum of all costs/Total number of costs)* total units sold
= (($5+$5.1+$5.3+$5.35+$5.6+$5.8)/6)* 1450
=$7769.58
No definitely not
Is this an assessment question?
Answer:
NPV = $-3,383.25
Explanation:
The NPV is the difference between the PV of cash inflows and the PV of cash outflows. A positive NPV implies a good investment decision and a negative figure implies the opposite.
NPV of an investment:
NPV = PV of Cash inflows - PV of cash outflow
PV of cash inflow =
$12,500,
× 1.1535^(-1) + 19,700,
× 1.1535^(-2) + 0× 1.1535^(-3) + 10,400.× 1.1535^(-2) = 31,516.7476
Initial,cost = 34,900
NPV = 31,516.7476 - 34,900 = -3,383.25
NPV = $-3,383.25
Answer:
If price is less than minimum average variable cost, resulting losses will cause firms to leave the industry.
Answer:
The correct answer is A
Explanation:
Sunk cost is the cost which is incurred by an entity and that can no longer be recovered. It is that cost which is not considered when making the decision to continue investing in the online project as it cannot be recovered.
In this case, city of Tustin incurred $10 million on the project for building a new community college and further it require $40 million to finish the project. The economist told the city council to ignore $10 million because it is a sunk cost which cannot be recovered.