Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.
Answer:D.
Someone is given responsibility for deciding how to meet the need.
Explanation:
Answer: "e. None of the answers above is correct."
Explanation: 1) If a bond sells for less than par, its yield at maturity is greater than its coupon rate.
2) If a bond sells at par, its current yield will be the same as its yield at maturity.
3) A bond selling for more than par will always have a lower capital gain than a par bond.
4) Both Incorrect.
At the least a channel of distribution firms consists of a producer and a customer. They are consumers when they use the products that have been produced, the products that have been produced, the products that have been produced.
Producer markets: To make a profit, producers purchase things and services, change them into marketable products, and then sell those products to customers. Farmers, factories, and construction firms are some examples of producers. A producer is in charge of discovering and starting a project, securing funding, employing writers, directors, and other important members of the creative team, and supervising every stage of pre-production, production, and post-production up to release.
To learn more about producer, click here.
brainly.com/question/14616889
#SPJ4
Answer:
The Eric's self-employment tax is $10109
Explanation:
The computation of the Eric's self employment tax is shown below:
= Net Self employment income × OASDI tax rate + Net Self employment income × MHI tax rate
= $132,150 × 6.2% + $132,150 × 1.45%
= $8,193.30 + $1,916.175
= $10109.475
The OASDI tax rate is also called social security tax and the self employment tax comprises of OASDI tax and MHI tax.