Answer:
b
Step-by-step explanation:
Answer:
2x^1+1
Step-by-step explanation:
Area=L X W
which means that (14x^4+7x^2) needs to be divided by 7x^2
factorise(14x^4+7x^2) which gives 7x(2x^2+1)
divide 7x(2x^2+1) by 7x^2
gives 2x^2 +1
Incomplete question. However, let's assume this are feasible regions to consider:
Points:
- (0, 100)
- (0, 125)
- (0, 325)
- (1, 200)
Answer:
<u>Maximum value occurs at 325 at the point (0, 325)</u>
<u>Step-by-step explanation:</u>
Remember, we substitute the points value for x, y in the objective function P = 2x + 1.5y.
- For point (0, 100): P= 2(0) + 1.5 (100) =150
- For point (0, 125): P= 2(0) + 1.5 (125) =187.5
For point (0, 325): P= 2(0) + 1.5 (325) = 487.5
For point (1, 200): P= 2(1) + 1.5 (200) = 302
Therefore, we could notice from the above solutions that at point (0,325) we attain the maximum value of P.
Answer:
Project A :
NPV : $703,888.64
IRR : 44.882%
Project B:
NPV : $5,241.26
IRR : 49.662%
Project B is more profitable
Step-by-step explanation:
The NPV gives the difference between the present value of cash inflow and cash outflow over a certain period of time.
The Internal rate of return is the discount rate which makes the NPV of an investment 0. It is used to estimate the potential return on an investment. Investments with higher IRR are said to be better than those with lower IRR value.
Using the net present value, (NPV) Calculator, the NPV for project A is : $703,888.64
The IRR of project A is : 44.882%
The NPV for Project B is : $5,241.26
The Internal rate of return (IRR) : 49.662%
From the Internal rate of return value obtained, we can conclude that, project B is more profitable as it has a higher IRR than project A.