Answer:
Minimum cycle time = time for longest task = 2.4 minutes
Maximum cycle time = sum of the times to complete all the tasks = 18 minutes
Step-by-step explanation:
For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.
For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.
Answer:
X/3 X is unknown, so it would be this until you figure out X
10.5, since 35 is between 30 and 40 ((30+40)/2), the mistakes that correspond with them are 9 and 12, the number in between them is 10.5 (9+12=21, 21/2 is 10.5)
Answer:
The inequality x+y<1 should look like the graph attached.
It should be a dashed line, not a solid line.