Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
The lemght could be 15 because a triangle has two long sides and one short one and the two are equivalent
It's called an obtuse angle.
Answer:
64.468
Step-by-step explanation:
Answer:
3x + 2y = 38, 3a + 2b = 38
Step-by-step explanation:
An equation may be defined as a statement that shows two mathematical expressions to be equal. It is to equate one thing to another thing.
In the context, two different equations for the situations are :
i). Let the shirt be represented by x
And the socks be represented by y
Therefore, according to the question,
3x + 2y = 38
ii). Let the shirt be represented by a
And the socks be represented by b
Therefore, according to the question,
3a + 2b = 38