Answer:
Explanation:
Cost
Machine - 800,000
Installation - 100,000
Training - 100,000
Total cost - 1,000,000
Contract price - 920,000
Using ratio to allocate the prices , we have
a)Machine price = cost of machine / total cost * total contract price
800,000/1,000,000*920,000 = 736,000
b) Installation price =cost of installation / total cost * total contract price
100,000/1,000,000*920,000 = 92,000
c) Training price = cost of training / total cost * total contra t price
100/1,000,000 * 920,000 = 92,000
736,000+92,000+92,000= =920,000