The answer to this question is Pyramid model. In pyramid mode, all information systems will be divided into different classes that will form a hierarchy and usually it is based on importance. The most important aspects will be placed on the top of the pyramid structure while the least important aspects will be placed on the very bottom.
Answer:
<em>Imposed project deadlines.</em>
Explanation:
The term of project management imposed deadline<em> refers mainly to the calendar-based dividing line used to determine a fixed time or date on which the project management team has projected and/or developed that the particular schedule of work and/or schedule of work events.</em>
Answer:
13.3%
Explanation:
OEE= Availability × Performance × Quality
Availability = Run Time/ Planned Production Time
Run time = 3*100 = 300 + 0.2* 300 = 1.2 *300 = 360 mins
Planned Production time = 24*60 = 1440 mins
Availability = 360/1440 = 1/4 = 25%..............1
Performance = (Ideal Cycle Time × Total Count) / Run Time
Ideal Cycle Time = 2 min (Only the processing time)
Total Count= 100+20 = 120
Performance = 2*120/360 =66.67% .............2
Quality = 100%-20% = 80%.......3
Frpm 1,2,3
OEE=25% * 66.67 % * 80% =
0.13334=13.3%