1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Nadusha1986 [10]
3 years ago
9

A kite flying in the air has a 78-string attached to it, and the string is pulled taut. The angle of elevation of the kite is 52

°. Find the height of the kite. Round
your answer to the nearest tenth.

Mathematics
1 answer:
Basile [38]3 years ago
5 0

Answer:

sine 52 degrees = height / 78

height = 78 * sine 52

height = 78 * 0.78801

height = 61.46478 feet

rounded to nearest tenth 61.5 feet

Step-by-step explanation:

You might be interested in
a mechanic buys $14.56 worth of parts from a supplier. if he pays for the parts with a $20 bill, how much change will he receive
Bond [772]
He will receive $5.04
3 0
3 years ago
Read 2 more answers
A healthy adult cheetah can run 110 feet per second. How fast can a cheetah run in miles per hour
blagie [28]
6600 /minute so... 396,000 /hour
7 0
3 years ago
mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days
4vir4ik [10]

Answer:

<em>Most likely time, </em>according to PERT (Program evaluation and review technique).

Step-by-step explanation:

PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.

Inside PERT, there are different defined times to accomplished an activity in a project, that is:

  • An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
  • A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
  • A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
  • An <em>expected time</em>, an statistical estimation.

Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":

  • "[...] in as few as 15 days"  is the <em>optimistic time</em>.
  • "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
  • "[...] but most likely will require 20 days" is the <em>most likely time</em>.

As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.

3 0
3 years ago
What is the chemical formula for copper(ll) sulfate?
Darya [45]
It should be A, CuSO4
7 0
3 years ago
A degenerate circle is:<br> I. a circle with radius r = 0.<br> II. a point.<br> III. a line.
o-na [289]

Answer: I and II only

Step-by-step explanation:

Radius=0 and a point

4 0
3 years ago
Other questions:
  • Alanina has 28$ in her account. she wants
    11·1 answer
  • Solve for p −160=22+8(3p−4)
    13·1 answer
  • Solve the following system of equations and show all work. y = 2x^2 y = –3x −1
    13·1 answer
  • Which of the following statements is true for inverse functions f(x) and g(x)?
    12·2 answers
  • Find the equation m=7/8 (5,-6)
    11·1 answer
  • Help ME! I’m literly struggling
    5·1 answer
  • An empty suitcase has a mass of 2 kilograms. Draw a bar model to find its mass in grams.
    11·1 answer
  • What is the solution to the equation? 13 3/4+X= 7 1/ 4​
    8·1 answer
  • Veronica’s favorite breakfast cereal costs $0.21 per ounce. How much would she spend on 16 ounces of cereal?​
    11·2 answers
  • Which equation represents the line that passes through points B and C on the graph
    7·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!