1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
IrinaK [193]
3 years ago
15

1. Sandra is trying to determine the height of a light pole at the corner of the block on

Mathematics
1 answer:
Vlad [161]3 years ago
7 0

Answer:

h = 5(tane)

Step-by-step explanation:

The diagrammatic representation of the question given is attached below ;

The height of the light pole, h = opposite side

Adjacent side = 5 feets

Angle of elevation = e

Using trigonometry ;

Tan e = opposite / Adjacent

Tan e = h / 5

Making h the subject ;

h = 5(tane)

You might be interested in
Which of the following best describes the slope of the line below?
alekssr [168]

Answer:

Zero

Step-by-step explanation:

the line is not going up or down therefore there is no slope

6 0
2 years ago
How much greater is this week’s median temperature than last week’s median temperature?
Scrat [10]

Answer:

5 degrees

Step-by-step explanation:

5 0
3 years ago
How would you do (k-3)/4 = 10 ?
givi [52]
Are you asking how to solve for k? In that case, multiply both sides by 4. Then add 3 to both sides:

(k-3) = 40
k = 43
3 0
3 years ago
An externally imposed project completion time sets the project duration at 75 days. The critical path of the project is establis
Katen [24]

Answer:

3 days

Step-by-step explanation:

This can be seen under Schedule management (Initiating)

Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because

Externally imposed project date = 75 days

Estimated duration of project = 75 days

Hence, a difference in these will be 0

However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration) .

Hence the maximum float in this case will be 0 + 3 = 3 days

8 0
3 years ago
I need help with this question I would appreciate it!!
Elden [556K]

3x - 5 = 10


3 × 5 - 5 = 10

7 0
3 years ago
Other questions:
  • What can you multiply to get 10 and add to get seven
    8·2 answers
  • A baker used 12 cups of batter to make muffins. It took 2/3 cup of batter to make 1 muffin. How many muffins did the baker make?
    9·1 answer
  • Chelsea and her friends are going to a movie. If popcorn is $3.99 and drinks are $1.75, what is the cost of two popcorns and thr
    6·2 answers
  • Can you give me the work and the answers for these please.
    5·1 answer
  • Y=3x-2 solve for x plz help 40 points!!!
    11·1 answer
  • Help me pleaseeeeeeeee​
    9·1 answer
  • Use the distributive property to write an equivalent expression.
    12·1 answer
  • Write and solve an equation for the following:
    13·1 answer
  • 5. What is the value of p in the equation?<br><br><br> p - 4 = -8<br><br> -2<br> -12<br> -4<br> - 32
    13·2 answers
  • I need help with this please I’m stuck.
    12·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!