plural noun: stakeholders
1.
(in gambling) an independent party with whom each of those who make a wager deposits the money or counters wagered.
2.
a person with an interest or concern in something, especially a business.
Answer:
Critical path = A-D-F-H
Duration = 22
Explanation:
Given:
Activity A B C D E F G H
Time 5 3 7 6 7 3 10 8
The objective is to identify the critical path and to find the time needed to complete this project
Solution:
The possible paths are as follows,
A-C-H = 5+7+8 =20
A-D-F-H = 5+6+3+8 =22
A-D-G = 5+6+10 = 21
B-E-G = 3+7+10 = 20
B-E-F-H = 3+7+3+8 = 21
a)
Critical is the path with the longest duration
Critical path =A-D-F-H
The duration is 22
b)
The duration to complete the project is as follows,
Duration = Length of critical path = 22

Option A is the correct answer
Answer:
$164,313.82
Explanation:
In this question we have to apply the present value formula i.e to be shown in the attachment
Provided that,
Future value = $0
Rate of interest = 9%
NPER = 20 years
PMT = $18,000
The formula is shown below:
= -PV(Rate;NPER;PMT;FV;type)
So, after applying the above formula the present value is $164,313.82
Answer:
B. Escalator Clause
Explanation:
An escalation clause is a clause in a lease or contract that guarantees a change in the agreement price once a particular factor beyond control of either party affecting the value has been determined. An important example of this is a contract that adjusts for inflation.