Answer and Explanation:
The computation of the overhead rate for each activity is as follows;
Overhead rate is
= Respective overhead cost ÷ Respective activity
For Machine setups
= ($202,800 ÷ 2,600 setups)
= $78 per setup
For Machining
= ($364,500 ÷ 24,300 machine hours)
= $15 per machine hour
For Inspection
= ($88,000 ÷ 1,600 inspections)
= $55 per inspection
In this way it is calculated
Answer:
Control limits for x_bar are between 59.076 and 60.924
Control limits for R are between 0.669 and 5.331
Explanation:
Given data:
x_bar = 60 mph
n = 10
R = 3 mph
Step 1: Factors (see table attached)
At n = 10, factors for computing control charts limits are,
A2 = Mean factor = 0.308
D3 = Lower range = 0.223
D4 = Upper range = 1.777
Step 2: Control limits for x_bar
Lower Control limit:
LCL = x_bar - A2*R = 60 - (0.308)(3) = 60 - 0.924 = 59.076
Upper Control limit:
UCL = x-bar + A2*R = 60 + (0.308)(3) = 60 + 0.924 = 60.924
The control limits for x_bar are between 59.076 and 60.924
Step 3: Control limits for R
Lower Control limit:
LCL = D3*R = 0.223(3) = 0.669
Upper Control limit:
UCL = D4*R = 1.777(3) = 5.331
The control limits for R are between 0.669 and 5.331
Hope this helps!
Answer:
Early tasks opposed to later tasks.
Explanation:
Shortening is a strategic procedure used by project managers to reduce or shorten a project's duration by cutting the duration of critical path tasks.
The rationale behind shortening of a project is basically to have a competitive advantage or edge in the market. In order to compete successfully, project managers are always expected to be spontaneous in bringing their company's goods and services to the market in a flash.
There are two important ways of shortening a particular project, these are;
1. Crashing.
2. Task splitting.
In project management, the longest task is considered to be the most effective and efficient candidate activities to shorten a project's duration.
In general, the better candidates for shortening are early tasks opposed to later tasks. The early start of tasks represents one of the primary date used in project scheduling and it's the earliest date a project manager commences an activity, with respect to all its predecessors and successors.
Early tasks usually involves the use of an easy approach to project kickoff while later tasks uses the difficult approach.
Answer:
D) $25,000
Explanation:
Even though Dana and Larry are married, since they are filing separate tax returns, then all the income that Larry must declare are his $25,000 earned as rental income.
If they were filing together, then they would declare $70,000 as combined income (= $25,000 + $45,000).
Answer:
18,500 WIP balance at September 30th
Explanation:
Job A3B
3,500 direct materials
5,000 direct labor
10,000 Overhead (200% of labor = 5000 x 200%)
18,500 WIP balance at September 30th
The cost added during October will be part of October calculation, on September we should work with September values.