Short answer yes. kinda long answer people can scan the photo and easily see or they can just look up the same image
The algorithm is as follows:
1. Start
2. bottles = 0
3. While bottles != 500
3.1 Create bottle
3.2 bottle = bottle + 1
4. Switch off machine
5. Stop
Explanation:
This begins the algorithm
1. Start
This initializes bottles to 0
2. bottles = 0
The loop is repeated until 500 bottles is created
3. While bottles != 500
This creates a new bottle
3.1 Create bottle
This increments the number of bottles by 1
3.2 bottle = bottle + 1
This switches of the machine after all bottles are created
4. Switch off machine
End algorithm
5. Stop
THANKS
Answer:
(b). dependency and hedging.
Explanation:
In the management of risk, four common approaches for reducing risk are;
i. <em>Avoidance</em>: Especially if a risk involved in the management of a resource (or project) poses or presents a negative consequence, the best way to manage the risk simply avoid it by making sure it doesn't happen. This can be by cancelling a project or restructuring it.
ii. <em>Adaptation</em>: Another way of managing the risk associated with a resource (human or non-human resource) is to control the risk either by increasing resilience or reducing vulnerability. This is called adaptation.
iii. <em>Dependency: </em>This means accepting the risk since every project or business has inherently in it some risk associated. Dealing with it might be a way out especially knowing that there might be some experience to be gained in order to tackle similar situation in the future.
iv. <em>Hedging: </em>This means transferring the risk to some other business or organization. An example might be to get an insurance to manage this risk. In this case, the risk is transferred to the insurance company.