Answer:
-963
Step-by-step explanation:
When the sign of the number with the greatest absolute value is positive
Well, that's incorrect because according to the Order of Operation [GEMS\BOMDAS\PEMDAS etc.], that -7 has to be distributed amongst all the other terms in parentheses. Besides, you did the wrong operation when you inserted that subtraction symbol in substitution of the parentheses, which means to MULTIPLY. So, the order goes as follows:
12 - 7[72]
-504 + 12 = -492 [OR 12 - 504]
-492 is your answer. You get it now?
We are given a function f ( x ) defined as follows:

We are to determine the value of f ( x ) when,

In such cases, we plug in/substitue the given value of x into the expressed function f ( x ) as follows:

We will apply the power on both numerator and denominator as follows:

Now we evaluate ( 2 ) raised to the power of ( 1 / 9 ).

Next apply the division operation as follows:

Once, we have evaluated the answer in decimal form ( 5 decimal places ). We will round off the answer to nearest thousandths.
Rounding off to nearest thousandth means we consider the thousandth decimal place ( 3rd ). Then we have the choice of either truncating the decimal places ( 4th and onwards ). The truncation only occurs when (4th decimal place) is < 5.
However, since the (4th decimal place) = 8 > 5. Then we add ( 1 ) to the 3rd decimal place and truncate the rest of the decimal places i.e ( 4th and onwards ).
The answer to f ( 1 / 2 ) to the nearest thousandth would be:

Answer:
the first one
Step-by-step explanation:
A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.
The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.
The second graph does not appropriately account for duration of predecessor tasks.
The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).