PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15
Answer:
25
Step-by-step explanation:
percentage calculator 40 is what percent of 160=25;)
30
Multiply 6 by5
Now try divide that answer by 6
:)
Answer: p(a given b) = p(a and b) / p(b)
a is the probability that they score.
b is the probability that they cross the blue line.
p(a and b) is given as .005
this is the probability that they cross the blue line and score.
p(b is given as .6
that's the probability that they cross the opposing blue line.
the formula becomes:
p(a given b) = .005 / .6 = .0083333333.....
that's what i get using the p(a given b) formula.
Step-by-step explanation:
Step 1. Isolate the variable x:



Step 2. Use the simplified inequality to graph:
- Select an OPEN point on x = -5
- Select a ray extending from -5 to positive infinity (GREATER than -5)
I hope this helps!