Answer:
a. scientific management
Explanation:
Scientific management -
Scientific management is also refers to as Taylorism .
According to this management practice , the work is analysed and synthesized in an appropriate manner and fashion , is referred to as scientific management.
The scientific experiments are conducted with proper procedure and management.
Hence , from the given information of the question,
The correct term is a. scientific management .
<span>If some activity creates positive externalities as well as private benefits, then economic theory suggests that the activity ought to be: </span>subsidized
Answer:
(a) $1.8 per machine hour
(b) $390 per setup
Explanation:
Given that,
Overhead allocated to the cutting cost pool = $410,400
Overhead allocated to the design cost pool = $666,900
Total machine hours = 228,000
Total number of setups = 1,710
Under activity based costing,
Overhead rate for cutting:
= Overhead allocated to the cutting cost pool ÷ Machine Hours
= $410,400 ÷ 228,000
= $1.8 Per Machine Hour
Overhead rate for design:
= Overhead allocated to the design cost pool ÷ Number of Setup s
= $666,900 ÷ 1,710
= $390 per set up
Kevin's profession is most likely a financial manager.