Answer:
The range of possible transfer is $ 3.25 to $ 3.50
Explanation:
Data provided:
The purchasing cost of the transistor = $ 3.50
The total number of transistors needed = 8,000
The production cost of the transistor = $ 4.00
The included variable cost = $ 3.25
The included fixed cost = $ 0.75
Now,
the fixed cost cannot be altered, thus it will be there
hence,
the variable cost will be the factor that will evaluate the decision i.e $ 3.25
therefore, the <u>range of possible transfer is $ 3.25 to $ 3.50</u>
Answer:
(B) Hardening sprints
Explanation:
Hardening Sprints are not allowed because the subject of hardening should be continuously address throughout normal Sprints.
Or if the question has the following options:
Which of the following is not allowed in Scrum?
a. Using Story Points
b. Hardening Sprints
c. Release Planning
d. Using Planning Poker
Answer:
(B) Hardening sprints
Explanation:
Using Story Points, Release Planning, Using Planning Poker are not mandatory but allowed. Only hardening sprints are not allowed.
Answer:C.TINSTAAFL Rating
Explanation:
Answer:
(i) The farm can cover its revenue using its total variable cost, therefore the farm will continue producing 200 units
(ii) The farm cannot cover its revenue using its total variable cost, therefore the farm will shut down
(iii) The two relevant points on supply curve will be: (Price = $12 & Quantity = 0) and (Price = $25 & Quantity = 200)
Explanation:
(i)According to given data, When output is 200 but price is $20, this price is equal to ATC, so the farm breaks even. But since this price is higher than AVC of $15, the farm can cover its revenue using its total variable cost, therefore the farm will continue producing 200 units.
(ii) When output is 200 but price is $12, this price is equal to ATC, so the farm makes economic loss. Also, this price is lower than AVC of $15, so the farm cannot cover its revenue using its total variable cost, therefore the farm will shut down.
(iii) The farm's supply curve is the portion of its Marginal cost (MC) curve above the minimum point of AVC. Since price equals MC, the two relevant points on supply curve will be: (Price = $12 & Quantity = 0) and (Price = $25 & Quantity = 200).
Answer:
Explanation:
gate City bank reconciliation statement as at December 31, 2018
Balance as per cash book 2400
Direct payment to the bank (loan) 520
Less bank charges (30)
Add bank interest 20
Adjustment 510
Adjusted cash book balance 2910
Balance as per bank statement 3,810
Less outstanding check (1300)
Add deposit in transit 400
Adjustment (900)
Adjusted bank statement balance 2,910