Answer:
0.60
Step-by-step explanation:
find the probability it is a 2:
0.40 / 1 = 0.4 or 40%
find the probability it isn't a 2:
1 - 0.4 = 0.6
The matrix represents the vertices of the rectangle after it is scaled by a factor of 3 is,
[ 0 12 12 0]
[ 0 0 12 6]
<h2>
We have to determine</h2>
Which matrix represents the vertices of the rectangle after it is scaled by a factor of 3?
<h3>According to the question</h3>
The vertices of the triangle are
The scale factor is 3.
<h3>The vertices of the triangle are scaled with the factor of 3 so the vertices are get multiplied by 3.</h3>
Therefore,
The vertices of the rectangle after scaled by the factor of 3 are,

The vertices of the rectangle after it are scaled by a factor of 3.
Therefore,
The matrix represents the vertices of the rectangle after it is scaled by a factor of 3 is,
[ 0 12 12 0]
[ 0 0 12 6]
To know more about Matrix click the link given below.
brainly.com/question/2489305
Answer:
1. Use the Adjacent and opposite side (Ignore the Hypotenuse)
Or use HERO'S FORMULA based on the information given
2. Area = 216cm^2
Step-by-step explanation:
There are three to four ways we can go about finding the area of a triangle. And a these would be dependent on the information given about the triangle.
From the question, you said the three side lengths are given. In such case, we employ the HERO FORMULA.
HERO FORMULA:
Area = √ s(s-a)(s-b)(s-c)
where s = 1/2(a + b + c)
a, b, c are the three sides
But since the question insisted that we use 1/2* base * height. Let's use our know of right angle to dissolve that.
A right angle triangle has three sides. The longest is always the Hypotenuse.
Let's take it this way.
Hypotenuse = 30cm
Opposite= 18cm
Adjacent = 24cm
Area = 1/2 * base * height
Area = 1/2 * 18 * 24
Area = 1/2 * 432
Area = 216cm^2
We ignored the longest side, (the Hypotenuse)
Answer: I think it’s skewed right
Step-by-step explanation:
Answer:
15
Step-by-step explanation:
PERT estimate is a measuring strategy that is based on a weighted average. It is used in measuring the uncertainty and risk via three estimates to determine an estimated likelihood for a project's cost or period of completion.
The formula is (O + 4M + P) ÷ 6
Where P is the most pessimistic = 29
M is the most likely = 12
O is the most optimistic = 10
Hence we have (10 + [4*12]+ 29) ÷ 6
= (10 + 48 + 29) ÷ 6
= 87÷6 = 14.5 ≈ 15
Rounded figure is equal to 15.
Hence the final answer to the question is 15