Answer: The correct answer is "b. Ace has done nothing to change its CERCLA liability."
Explanation: CERCLA is the Comprehensive Environmental Response, Compensation and Responsibility Act and was designed to promote cleaning, maintenance and protection of the environment against hazardous waste.
Those responsible for releasing dangerous substances are identified to take care of their cleaning through the superfunds, therefore by creating the new corporation and transferring the assets: Ace has done nothing to change its CERCLA liability.
Answer:
Dividend yield = 5.54%
The expected capital gains yield = 6%
Explanation:
Next Dividend (D1) = $1.44
Growth rate (g) = 6%
Required return (Ke) = 6% + 5.54% = 11.54%
Ke-g = 11.54% - 6% = 5.54%
Price = D1 / (ke / g) = 1.44 / 5.54% = $25.9927 = $26
a. Dividend yield = D1 / Price = $1.44 / $26
Dividend yield = 0.05538
Dividend yield = 0.0554
Dividend yield = 5.54%
b. The expected capital gains yield = Required return (Ke) - Dividend yield
The expected capital gains yield = 11.54% - 5.54%
The expected capital gains yield = 6%
Answer:
consistency corporate culture.
Explanation:
Since in the situation it is given that the corporation follows the culture that means they are strict to the rule and regulations along with the time scheduling that are fixed for day to day activities so that the business could be conducted in the methodical manner so here we can say that the culture of the corporate is consistent that means it is same as before and the same should be applied in near future
The correct answer to this open question is the following.
The key project management strategies that may have been used to minimize Go-live problems with the HP SAP Go-live process are the following.
1.- To avoid steps missing, checkpoint is necessary. 2.- Senior management must be informed about development issues, infrastructure, communication, testing, training, conversion, and operations. 3.- Collect all the information available from project teams. 4.- Take into consideration the information of team leaders and users. 5.- Apply readiness review after five or six months to see if the target date is possible.
Answer:
Explanation:
For computing the cost of inventorying, we have to apply the formula which is shown below:
= Total costs ÷ Number of items
1. Cost of inventorying = Total costs ÷ Number of items
= $125 ÷ 100 items
= $1.25
Total cost = $100 + $25 = $125
2. Cost of inventorying = Total costs ÷ Number of items
= $150 ÷ 150 items
= $1
Total cost = $100 + $25 + $25 = $150
3. Cost of inventorying = Total costs ÷ Number of items
= $175 ÷ 160 items
= $1.10
Total cost = $100 + $25 + $25 + $25 = $175
$25 is the each worker pay
To minimize the cost we required two workers as the cost of inventorying is lesser than other two.