Answer:
15 days
Step-by-step explanation:
Let x be the number of days needed for B to complete the job. Then x-5 is the number of days needed for A to complete the job.
In 1 day,
- A completes of all work;
- B completes of all work.
Hence, in 1 day both A and B complete of all work. A and B working together can do a work in 6 days. Then
Solve this equation:
If then that is impossible. So, B needs 15 days to complete the work alone.
If I’m correct this is supposed to be a decimal ( here we use the dot not the comma ) but if so then 32.52 a good way to remember is 5 or more let it sore (meaning round up) four or less let it rest (meaning it stays the same)
Answer:
24
Step-by-step explanation:
The given points are (4,8) & (9,-4)
slope of a line = <u>Y2 - Y1</u>
X2 - X1
====> <u>(-4) - 8</u> = <u>-12</u>
9 - 4 5