Answer:
7 workers will be required
Explanation:
We will define actual time required to do a job
= Standard time required for producing each unit x Worker efficiency (%)/100
= 11.65 x 115/100
= 13.3975 minutes
Total available minutes in 4 days = 4 days x 8 hours/ day x 60 minutes / day = 1920 minutes
Therefore ,
Number of units which can be produced by 1 worker in 4 days = 1920 /13.3975
Number of units to be produced = 1000 units
Therefore,
Number of workers required
= Number of units to be produced / Number of units which can be produced by 1 worker in 4 days
= 1000 x ( 13.3975 /1920)
= 6.977 ( 7 rounded to nearest whole number )
Answer:
B) making warranties easier to understand.
Explanation:
The Magnuson Moss Warranty Act of 1975 governs consumer product warranties. Manufacturers are not required to offer product warranties, but when they do, they are required to provide clear and detailed information about warranty coverage. This law applies only to products, it doesn't apply to services.
Answer:
<em>Monetary policy</em> consists of management of money supply and interest rates, aimed at achieving macroeconomic objectives such as controlling inflation, consumption, growth, and liquidity.
Answer:
1. Yes, overshooting is consistent with PPP. Investors forecast the expected exchange rate based on the theory of PPP. When there is some change in the market, the investors know the exchange rate will change to equate relative prices in the long run. This is why we observe overshooting in the short run. The investors incorporate this information into their short-run forecasts.
2. Exchange rates are volatile in the short run. The theory's implication that there is exchange rate overshooting (in response to permanent shocks) is one explanation for short-run volatility in
exchange rates.