Answer:
C.
Explanation:
The critical path is the sequence of activities between a project's start and finish that takes the shortest time to complete.
Answer:
$214,800
Explanation:
The amount paid is the sum of the amount declared and the difference in amounts payable.
dividends paid = $209,800 +50,400 -45,400
dividends paid = $214,800
Answer:
-$380,789
Explanation:
Dear Portfolio = [(1,50,000)2 + (2,50,000)2 + 2(0.8)(1,50,000) ( 2,50,000)]0.5
= [$22500000000 + $62500000000 + $60000000000]0.5
= ($145000000000)0.5
= $380,789
Explanation:
The basic principle for the risk management are as follows -
1. Do not accept unnecessary risk - unnecessary risk comes without commensurate benefits. Only absolutely necessary while Missions must be undertaken while exposing personnel and resources to the lowest possible risk.
2. Make decisions at appropriate levels to establish clear accountability, which means those responsible for success or failure must be involved in the risk decision making.
3. Accept risks when benefits outweigh the costs.
4. Integrate operational risk management (ORM) into operations and planning at all levels.
Answer:
After 18.44 year loan will be paid
Explanation:
We have given an entrepreneur borrows $500,000 today.
So total amount is $500000
Annual payment is of $70000
Rate of interest r = 11.5 %
We have to find the time period
We know that total amount is given by
, here A is total amount , P is yearly paid amount, r is rate of interest and n is time period
So 

Taking log both side


n = 18.44 year
So after 18.44 year loan will be paid