Answer:
23 days
Step-by-step explanation:
We are told that the stadium holds 7500 individuals.
Now, if 600 seats have already been made, It means the number of seats left to be made to complete the stadium = 7500 - 600 = 6900 seats
We are told that 300 seats can be made in a day. Thus, number of days to be used to finish the remaining seats = 6900/300 = 23 days
Thus, it will take 23 days to complete all the 7500 seats.