Answer:
2nd and 3rd
Step-by-step explanation:
You should use 22/7 when you are dealing with other fractions.
Answer:
49
Step-by-step explanation:
Let Thomas's age=x, so Huilan's age = x-11;
x+(x-11)=87
2x=98
x=49
so, Thomas's age is 49
Answer:
3 days
Step-by-step explanation:
This can be seen under Schedule management (Initiating)
Project float is simply the difference between the completion period externally imposed and the estimated time duration of the project (usually this is equal to the critical path length). The difference in this case is 0 because
Externally imposed project date = 75 days
Estimated duration of project = 75 days
Hence, a difference in these will be 0
However, a standard deviation of 3 days was giving (This implies that there is a +/- 3 days in the critical path from the estimated project duration)
.
Hence the maximum float in this case will be 0 + 3 = 3 days