Answer:
240 hours
Step-by-step explanation:
One person hour is a unit indicating the rate at which one person is working on the project .
The company estimates that it will take 2880 person- hours to complete the job
So let's determine how many hours it will take 12 workers to complete same job
The rate = 2880 person/hour
12 persons or workers =( 2880 person/hour)/12 persons
12 persons or workers = 2880/12
12 persons or workers=240 hours
It will take 12 workers 240 person hour to finish the project.
Thank you
Answer:
8 feet
12 inches equals 1 foot, so 8 inches is a lot smaller than 8 feet.
<span>Nadine mixes a juice solution that is made from 3 gallons of an 80% juice solution and 1 gallon of a 20% juice solution. What is the percent concentration of the final solution? =</span>65%
If line AB and BC are intersecting at point B and ray BD bisect the angle ABC, then the value of x is 23
The line AB and BC are intersecting at point B.
Ray BD bisect the angle ABC
∠ABD = x+8 degrees
∠ABD=∠DBC = x+8
Because the ray BD bisect the ∠ABC, so ∠ABD and ∠DBC will be equal
∠ABD+∠DBC= 4x-30 degrees
Because both are vertically opposite angles
Substitute the values in the equation
x+8 + x+8 = 4x-30
2x+16 = 4x-30
2x-4x = -30-16
-2x = -46
x = 23
Hence, if line AB and BC are intersecting at point B and ray BD bisect the angle ABC, then the value of x is 23
The complete question is
Line AB and BC are intersecting at point B and ray BD bisect the angle ABC. What is the value of x?
Learn more about angle here
brainly.com/question/28451077
#SPJ1