Answer:
d. Milestones are developed during risk planning.
Explanation:
A milestone is a typical measuring point used when establishing cost control. Which of the following does NOT accurately describes the use of cost control milestones?Select one:a. Project managers and sponsors often decide the number of milestones jointly.b. Milestones are often identified in the project charter.c. Project managers can use their cash flow projections to determine the funding needed to reach each milestone.d. Milestones are developed during risk planning.
<u>ANSWER</u>
It is not correct that milestones are developed during risk planning but rather they are developed during Project budgeting where the deliverables are identified in terms of the cost to achieve them. Truly as stated in the scenario's options, Project managers can use their cash flow projections to determine the funding needed to reach each milestone. It is in the project planning phase that these milestones are established by Project managers and sponsors jointly.
Answer:
A. $194, 035
Explanation:
Predetermined Manufacturing overhead Rate = Estimated total overheads / Estimated direct labor hours
Predetermined Manufacturing overhead Rate = $176,000 / 13,700
Predetermined Manufacturing overhead Rate = $12.85 / direct labor hour
Actual Labor hours = 15,100 hours
Manufacturing overhead allocated = $12.85x 15,100
Manufacturing overhead allocated = $194,035
The correct option is A. $194, 035
Answer:
True
Explanation:
This is probably one of the greatest issues that cartels around the world face, since their agreements are difficult to maintain because it is very difficult to control the price and output policies of its members.
Even the largest cartel in the world, the Organization of the Petroleum Exporting Countries (OPEC), has problems when it comes to monitoring the petroleum output of its members. When some countries need more money they just increase their petroleum production even if the rest of the cartel doesn't agree with it.
Answer:
a. Insurance expense for the month of march
= ($3,840 / 12 months) * 1 month
= $320 per month
b. Balance in prepaid insurance as of March 31
= ($3,840 / 12 months) *11 months remaining
= $3,520
c. Equipment rent expense for the month of April
= ($23,160 / 24 months) * 1 month
= $965
d. Balance in prepaid equipment rental as of April 30
= Nil ($0) as it is not mentioned that payment has been made, it is only mentioned that two year rental contract has been entered into.