Answer:
1a. $2.67 cost per unit
1b. $0.3 cost per unit
1c. Yes
Explanation:
1a. Calculation for what will be the inspection cost per unit If an inspector is hired
The following details were given in the question.
Defective average =3/100= 0.03
inspection rate = 30 per hour
Cost of inspector = 8 per hour
Correction cost = $10 each
Using this formula
Hired inspector =Cost per hour/Current production rate per hour
Let plug in the formula
Hired inspector=8 per hour/30 rate per hour
Hired inspector =0.267×100
Hired inspector=$2.67 cost per unit
1b. Calculation for what will be the defective cost per unit If an inspector is not hired
Using this Formula
No inspector=Defect rate %/Cost per defective
Let plug in the formula
No inspector= 3/100×$10
No inspector= $0.3 cost per unit
1c. Based on the above calculation the inspector should be hired.
It is more likely that you should interview all the 6 applicant's or people. You only have a small number of incumbents so you can interview all of that people in just a few hours. They all part of the job analysis process.
Answer:
Rehearsal
Explanation:
The process Randy used to encode the number into longer-term memory is called rehearsal
<span>B .There are 24 days remaining in July (31 - 7 ); 31 days in August; 30 days in September; and 5 days in October (24 + 31 + 30 + 5 = 90 days).
</span>
The days are not only based on estimation but on Accurate number of days in each month. Since it is written in july 7 then its maturity will be on october 5