Answer:
Step-by-step explanation:
Let d be the common difference.
a₁₀ = a₁ + (10-1)d
13 = -5 + 9d
d = 2
Answer:
1001.11
Step-by-step explanation:
$2200/monthxhfhfjfjf
Domain: -∞<x<∞
Range: -∞<x<∞
X-Intercept: x=0
Y-Intercept: y=0
Increasing on the interval of 0<x<∞
<span>Decreasing on the interval of -∞<x<0
</span>When A=0, the graph equals y=0
- When A is greater than 1, it makes the graph skinnier than <span>f(x)=|x|
- When A is less than 1 but greater than 0, it makes the graph fatter than </span><span>f(x)=|x|
- When A turns negative, it flips the graph upside down.
-When B is greater than 0, it translates the graph to the right
- When B is less than 0, it translates the graph to the left
When C is greater than 0, the graph moves upwards
When C is less than 0, the graph moves downwards</span>
Answer:
Option C) 146.5
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 130 weeks
Standard Deviation, σ = 10 weeks
We are given that the distribution of completion time is a bell shaped distribution that is a normal distribution.
Formula:

P(X<x) = 0.95
We have to find the value of x such that the probability is 0.95
P(X < x)
Calculation the value from standard normal z table, we have,

The project should be completed in 146.5 weeks or less.
Hence, 146.5 weeks should be set the due date such that there is a 95 percent chance that the project will be finished by this time.