1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Juliette [100K]
2 years ago
8

Find the solution of given expression

xFormula1" title=" \sqrt{2545 \times 2545} " alt=" \sqrt{2545 \times 2545} " align="absmiddle" class="latex-formula">


​
Mathematics
2 answers:
poizon [28]2 years ago
7 0

Answer:

√{2545×2545}=√2545²=±2545

kiruha [24]2 years ago
6 0

Answer:

Answer:

\sqrt{2545 \times 2545}  \\  = 2545

Hence,The Answer = 2545

You might be interested in
Please I need some Help! If I fail this Im literally dead!
enyata [817]

Answer:

Then study bro but here is your ans

Step-by-step explanation:

7 c

8 a

8 0
2 years ago
Equivalent to the expression of 23.6-2times3 to the power of 0 divided by 2
Sliva [168]
It'd be 2 I think but I'm not good at math
5 0
3 years ago
Which table shows a proportional relationship between x and y help me and earn 20 points
babunello [35]

Answer:

the answer is A

Step-by-step explanation:

i said a because

5×5=25

6×5=30

8×5=40

5 0
2 years ago
Read 2 more answers
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minute
Maurinko [17]

Answer:

Minimum cycle time = time for longest task = 2.4 minutes

Maximum cycle time = sum of the times to complete all the tasks = 18 minutes

Step-by-step explanation:

For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.

For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.

6 0
3 years ago
029494737+8489949494
skelet666 [1.2K]

Answer:

8519444231

I hope this helps!

4 0
2 years ago
Read 2 more answers
Other questions:
  • Find the points on the graph of y=sec x, 0 x 2 where the tangent is parallel to the line 3y-2x=4
    10·1 answer
  • a pitcher of fruit punch holds 2 gallons. if 9 people share the entire pitcher equally, how much punch does each person get?
    15·1 answer
  • Please help thank you.
    11·1 answer
  • Give two real-world situations that could be represented by the value 30
    8·1 answer
  • How many ounces of trail mix are in a bag that weighs 0.5675 kilograms? Input only numeric values. (1 pound = 0.454 kg and 1 pou
    11·1 answer
  • Use elimination to solve each system of equations. 1/3x-y=-1 and 1/5x-2/5y=-1
    11·1 answer
  • Can someone help me I don’t get it
    10·1 answer
  • Which expression is equivalent to ^3 square root of 54x + 3^3 square root of 2x, if x ≠ 0
    5·1 answer
  • Thanks to the rise of texting, emojis are becoming increasingly common. What does this suggest about graphics?
    14·1 answer
  • Help me and i will give u a brainlliest
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!