Answer:
108,280.22
Explanation:
Certainty equivalent is solved by taking the inverse utility function from the expected utility of a random wealth variable
U(x) = x^1/4
U^-1(x) = x^4
U^-1(x) === x^4
CE(x) = x^4
Salary Bonus Total income U(x)= x^(1/4) P(x) U(x)*P(x)
80000 0 80000 16.82 1/7 2.4
80000 10000 90000 17.32 1/7 2.47
80000 20000 100000 17.78 1/7 2.54
80000 30000 110000 18.21 1/7 2.6
80000 40000 120000 18.61 1/7 2.66
80000 50000 130000 18.99 1/7 2.71
80000 60000 140000 19.34 1/7 <u>2.76</u>
Sum <u>18.14</u>
CE(x) = 18.14^4
CE(x) = 108280.22
So therefore, the certainty equivalent of this job offer is 108,280.22
Answer: (D) Accept the risk
Explanation:
According to the given question, the one of the best solution is to accept the risk as the 2 given risks in the project cannot be removed or also outsourced from the given project scope.
Accepting the risk is one of the risk retention process in which we sometimes cannot avoid the given risk in the risk management and it is commonly found in the various types of investment process and also in the business.
On the basis of the given scenario, we could not eliminate the two risks in the project so the best solution is to using the risk acknowledgement due to some limitations. Therefore, Option (D) is correct answer.
Answer:
break even point in unit =5440 units
break even point in sales = $544000
total sale = $680000
Explanation:
given data
Current operating income = $34,000
Selling price = $100
margin ratio = 25%
to find out
Bay Area Cycle’s break even point in units and total sales dollars
solution
we get here first break even point that is express as
break even point in unit =
..................1
break even point in unit =
break even point in unit =5440 units
so
break even point in sales =
..................2
break even point in sales = 
break even point in sales = $544000
and
total sales will be
total sale =
..................3
total sale =
total sale = $680000
Answer:$100
Explanation:
Accounting profit is total earnings less total cost.
Accounting profit = Total revenue - Total cost
$150 - $50 = $100
Economic profit = Accounting profit - Opportunity cost
$100 - ($20 ×5) = 0
Answer:
$17.97 per unit
Explanation:
Using weighted average method, Equivalent units = Units that are completed during the period + Equivalent units in process at the end of period.
Equivalent units = 8,500 + 2,000*90%
Equivalent units = 8,500 + 1,800
Equivalent units = 10,300
Cost per equivalent unit for materials = (Beginning costs + Current costs) / Equivalent units
Cost per equivalent unit for materials = ($13,000 + $172,100) / 10,300 units
Cost per equivalent unit for materials = $185,100 / 10,300 units
Cost per equivalent unit for materials = $17.97 per unit