Distance from home to store = 4 * 0.5 = 2 miles.
Time taken to return home = (2/12) * 60 =10 minutes.
Total distance traveled = 2 * 2 = 4 miles.
Total time taken = 30 + 10 = 40 minutes.
Average speed for entire trip = total distance / total time in hours.
Answer:
X^3 AS THE NUMERATOR 8 AS THE DENOMINATOR
Step-by-step explanation:
B.) 37.5.. First you place all the numbers in order from least to greatest. Your mean is 25...and ur upper quartile because the 4 #'s fall even u add 35 and 40 and divide by 2... Which gives u upper quartile of 37.5 and lower quartile of 9. Hope this helps :)
<u>Complete Question:</u>
Janeel has a 10 inch by 12 inch photograph. She wants to scan the photograph, then reduce the results by the same amount in each dimension to post on her Web site. Janeel wants the area of the image to be one eight of the original photograph. Write an equation to represent the area of the reduced image. Find the dimensions of the reduced image.
<u>Correct Answer:</u>
A) 
B) Dimensions are : Length = 10-x = 3 inch , Breadth = 12-x = 5 inch
<u>Step-by-step explanation:</u>
a. Write an equation to represent the area of the reduced image.
Let the reduced dimensions is by x , So the new dimensions are

According to question , Area of new image is :
⇒ 
⇒ 
⇒ 
So the equation will be :
⇒ 
b. Find the dimensions of the reduced image
Let's solve : 
⇒ 
⇒ 
⇒ 
By Quadratic formula :
⇒ 
⇒ 
⇒ 
⇒
x = 15 is rejected ! as 15 > 10 ! Side can't be negative
⇒ 
Therefore, Dimensions are : Length = 10-x = 3 inch , Breadth = 12-x = 5 inch
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.