Answer: not, I wouldn't reccomend to borrow from a bank at 18% annual
Explanation: You will pay more, as montlhy interest would be 1.5% and for the 60 days you will pay 3% interest for the loan (18/12*2).
Example:
Price $ 100
with 2% of discount by paying within 10 days would be $98
And if you ask for a loan of $98 (that is the amount you need to pay with the discount) in 60 days you must pay to the bank $100.94 (98*1.03)
Answer: The answer is provided below
Explanation:
1. Underfinancing: One main reason that cause budget overrun and less than expected benefits is underfinancing. Allocation of an adequate amount of budget to project at the beginning will lead to a budget overrun or failure.
2. Unfeasible Cost Estimates: Estimation of cost is a vital process in a project and another common reason for budget overrun. When the cost is calculated by inexperienced or unqualified personnel, the project is going to face budget overruns.
3. Underestimating the Project Complexity: Big projects are usually at the risk of overrunning its budget as a result of bigger complications that may arise during its execution.
4. Lack of Resource Planning: When one fails to plan the resources that are available effectively, then this would lead to a budget overrun and less benefits. A common mistakes that cause overrun is failure to estimate the resources which would be utilized during the project.
Answer:
$1,443.75
Explanation:
The total cost for paving Sam's portion of the road = $35 per linear foot x 110 front feet = $3,850
If the city is going to pay 25% of the total cost, then it will pay $962.50, that would leave a total of $2,887.50 to be paid between Sam and his front neighbor. So Sam's share = $2,887.50 / 2 = $1,443.75
All parties in the chain of distribution of a defective product are strictly liable for the injuries caused by that product.
Chain of distribution refers to everyone involved in a transaction of a product from the beginning stages to the end when the consumer has the product. Strict liability is a doctrine that states all parties in the chain of distribution of a defective product are liable for the damages caused by it.
Answer:
It will take 30.10 year
Explanation:
We have given initial investment $500000
Future value = $ 1 million = $1000000
Rate of interest r = 1.79 %
We have to find the time taken to reach the amount $1000000
We know that future value is equal to 


Taking log both side

n×0.0077 = 0.3010
n = 39.09 year
Now in second case rate of interest
r = 2.34 %
So 


taking log both side
log 2 = n log 1.0234
n×0.01 = 0.3010
n = 30.10 year