Answer:
D1 = $4.085
D2 = $4.46
D3 = $4.86
D4 = $5.01
D5 = $5.16
Explanation:
As per the data given in the question,
DO = $3.75
Dividend expected to grow = 9%
Dividend grow later = 4%
D1 = DO(1+ Dividend1) = $3.75(1+9%)
=$3.75(1.09)
=$4.085
D2 = DO(1+ Dividend1 )( 1 + Dividend2)
= $3.75(1+9%)(1+9%)
= $4.46
D3 = DO(1+Dividend1)(1+Dividend2)(1+Dividend3)
= $3.75(1+9%)(1+9%)(1+9%)
= $4.86
D4 = DO(1+Dividend1)(1+Dividend2)(1+Dividend3)(1+Dividend later)
= $3.75(1+9%)(1+9%)(1+9%)(1+3%)
= $5.01
D5 = DO(1+Dividend1)(1+Dividend2)(1+Dividend3)(1+Dividend later)(1+Dividend later)
= $3.75(1+9%)(1+9%)(1+9%)(1+3%)(1+3%)
= $5.16
Answer:
Option A is the correct answer - Linda, whose moral reasoning is based on the approval of other people
Explanation:
In stage three of Kohlberg's theory of moral development, the individual (such as Linda, mentioned in the question) set out to do the things that are considered “right” because it is good, not only for the family, but also for the school, church or peer group.
This stage, often known as the "good boy/good girl" stage, has morality, often spelt out as acting in conformity to what the social group general requires to be right and moral.
Answer: 2 3 5 7
Explanation:
This is the answer that i got
Answer:
$143,200
Explanation:
Given that,
Work in process inventory at the beginning = $24,000
Direct material = $55,400
Direct labor = $28,600
Applied manufacturing overhead = $53,200
Work in process inventory at the end = $18,000
Cost of goods manufactured for June:
= Work in process inventory at the beginning + Direct material + Direct labor + Applied manufacturing overhead - Work in process inventory at the end
= $24,000 + $55,400 + $28,600 + $53,200 - $18,000
= $143,200
Answer:
A
Explanation:
Probability, impact
The purpose of Perform Qualitative Risk Analysis is to determine what impact the identified risk events will have on the project and the probability they will occur. It also puts risks in order of priority according to their effects on the project objectives and this is done by assigning s a risk score for the project. This boosts the chances of sucess of a project.