Answer:
p(on schedule) ≈ 0.7755
Step-by-step explanation:
A suitable probability calculator can show you this answer.
_____
The z-values corresponding to the build time limits are ...
z = (37.5 -45)/6.75 ≈ -1.1111
z = (54 -45)/6.75 ≈ 1.3333
You can look these up in a suitable CDF table and find the difference between the values you find. That will be about ...
0.90879 -0.13326 = 0.77553
The probability assembly will stay on schedule is about 78%.
Answer:
11.95 - 7.95 = 4
4/7.95 = 0.50314465
0.50314465 X 100= 50.314465
50% rounded to 1dp
Shortcut: you notice that the curve passes through (1,0)
Only log function passes this point.
Answer : This is because when 5z minus 5z, it is nullified, with no way to determine the value of z. 5z - 5z = 0
That is why there is no solution for this equation.
Hope this helps. - M
Answer:
21
Step-by-step explanation:
1 side = 6 plants (including one in the corner)
3 sides = 5 plants each
6+15 = 21