Under normal conditions, a firm's expected ROE would probably be higher if it financed with short-term rather than with long-term debt, but using short-term debt would probably increase the firm's risk.
Option A
<u>Explanation:
</u>
In business finance, the productivity of an undertaking, also defined as net assets or asset minus debt, is a calculation of its viability with respect to equity.ROE is a calculation about how well funds are used to produce increases in profits.
Companies are able to fund themselves with stocks and bonds. A business will raise its investment value by increasing the number of debt capital compared to its equity capital. There was a misunderstanding. Then you see that the new company has a better ROE because of its financial resources as you split the net income per shareholder's capital stock.
<span>9.20 percent
Re= 0.036 +1.2(0.085) = 0.138
Re= [($1.10 x 1.02)$19] +.02 = 0.0790526
ReAverage = (0.138 + 0.0790526)/2 = 0.108526
WACC = (1/1.65)(0.108526) + (0.65/1.65)(0.098)(1-0.32) = 9.20 percent</span>
Answer:
Adjusted Bank Balance = $85,000
Explanation:
Adjustment of bank balance is a bank reconciliation procedure, that is used to match the amount in the bank statement with the amount in the company's balance sheet.
To adjust the bank balance, particulars that need to be subtracted or added to the bank statement balance has to be identified and treated accordingly.
For this example, the adjusted balance is calculated thus:
Adjusted bank balance = (Bank statement balance) - (outstanding checks) +(deposit in transit)
Adjusted Bank Balance = 78,000 - 2,400 + 9,400 = $85,000
Note:
outstanding checks are subtracted because they are payments to be made made by the company, representing a liability to the company (payer)
deposit in transit is an income to the company that has not been credited yet, but that will be credited.
For a 13-person team, The number of extra workers that should be hired to meet the labor hours needed without overtime is 7.
<h3>What is Labor hours?</h3>
This is a term that connote the total hours of workers that are said to be having or getting an hourly wage and they are the ones who are said to be directly employed on the site of a building, public works project, etc.
Note that "Labor hours" is one that entails hours of work that has been carried out by workers who have been employed by the general contractor or the subcontractors that are found to be working on the project.
Learn more about labor hours from
brainly.com/question/24868261