8 percent. The answer to 4$is what percent of 50$ is 8%
Answer:
x=1,y=-2
Step-by-step explanation:
Answer:
7 and 8
Step-by-step explanation:

(x+3)(x+4)

(x+2)(x+6)
The expected duration of the activity is 29 days and 4 hours.
Step-by-step explanation:
Step 1:
The optimistic time,
= 25 days,
The most likely estimate,
= 29 days.
The pessimistic time,
= 34 days.
According to PERT, the expected duration of the activity, 
Step 2:
By substituting the given values, we get
0.1666 days = 
29.1666 days approximately equal 29 days and 4 hours.
Its known as the signature line