<u>Full question:</u>
A _____ is a deliverable at the lowest level of the WBS that represents the level of work that the project manager uses to monitor and control the project.
a) WBS dictionary
b) Budget item
c) Line item
d) Work package
Option D
A Work package is a deliverable at the lowest level of the WBS that represents the level of work that the project manager uses to monitor and control the project.
<u>Explanation:</u>
Work packages are the tiniest unit of activity that a project can be split down into when designing your Work Breakdown Structure (WBS). It can aid you to recognize the aspects you needed to prepare costs and work hours and then observe and maintain the application to completion.
Work packages can be recorded, cost evaluated, observed, and measured. Work packages provide for contemporary work to be performed on different components of a project in resemblance by multiple teams. Each team understands the tasks specified for the work package and finishes them by the specified deadline.
Basic steps start with opening the program, clicking on File, then clicking on New for a new document.
Most programs open a new blank document when you open he program.
Answer:
Trace Precedent
Explanation:
Trace Precedent is a Microsoft Excel tool that is mostly used in auditing work to evaluate the connection or linkage between the cells in a spreadsheet. It is used to display the cells that are referred to by a formula in the selected cell. This is to locate the basis of an error in knowing how the formulas are adapted.
This can be done by clicking on the Formulas tab, then click on Formulas Auditing, then click on Trace Precedents.
Hence, in this case, the correct answer is TRACE PRECEDENTS.
country or origin is usually the first character of a vin #
Answer:
language and interpersonal communication, basically it would make someone antisocial.