Answer:
.094
Step-by-step explanation:
Long division is really annoying, so here we go. Have it written on your paper and follow along.
When doing long division, you want to ignore the decimal until the very end. So how many times does 37 fit into 34? It doesn't, so write a 0 on top. Instead ask how many times it can fit into 347. It can only fit 9 times, so write the 9 next to the 0. Now multiply 37 times 9, since it can fit in 9 times. Place that number (333) under the 347. Subtract that and write the new number underneath (14). Bring down the 8 and add it to the end of your new number (now 148). How many times does 37 fit into 148? It goes in 4 times perfectly. Write the 4 on top, and now multiply 4 times 37, since it goes in 4 times. Put that number (148) below the original 148, subtract, and they cancel out. You're done with the problem! Add the decimal back in. Since there 3 numbers after the decimal in 3.478, the decimal will go before 3 numbers in your answer. Hope this helped!
Answer:
a. The percentage of vehicles who pass through this construction zone who are exceeding the posted speed limit =90.82%
b. Percentage of vehicles travel through this construction zone with speeds between 50 mph and 55 mph= 2.28%
Step-by-step explanation:
We have to find
a) P(X>40)= 1- P(x=40)
Using the z statistic
Here
x= 40 mph
u= 44mph
σ= 3 mph
z=(40-44)/3=-1.33
From the z-table -1.67 = 0.9082
a) P(X>40)=
Probability exceeding the speed limit = 0.9082 = 90.82%
b) P(50<X<55)
Now
z1 = (50-44)/3 = 2
z2 = (55-44)/3= 3.67
Area for z>3.59 is almost equal to 1
From the z- table we get
P(55 < X < 60) = P((50-44)/3 < z < (55-44)/3)
= P(2 < z < 3.67)
= P(z<3.67) - P(z<2)
= 1 - 0.9772
= 0.0228
or 2.28%
Hello.
We have:
- A point that the line passes through
- The slope of the line
Plug the values into the Point-Slope Formula:





I hope it helps.
Have a nice day.

Fist you need to substitute the value of R into the equation
25-6(3)
Now you simply
First multiple 6(3)
25-6(3)
25-18
Now solve!
25-18
7
The answer is 7