Answer:
the earned value of the project is $9,900
Step-by-step explanation:
The computation of the earned value of the project is shown below:
As we know that
CPI = Earned value ÷ Actual cost
1.1 = Earned value ÷ $9,000
So, the earned value is
= 1.1 × $9,000
= $9,900
hence, the earned value of the project is $9,900