It can be said that kent and julie have Low Inter-rater Reliability.
<h3>
What is Inter-rater Reliability?</h3>
- Inter-rater reliability is a statistical metric used to assess the degree of consensus among various judges or raters.
- It is employed as a method of evaluating the accuracy of the responses generated by various test items.
- A test's lower inter-rater reliability may be a sign that its questions are obscure, difficult to understand, or even superfluous.
- The percentage of items that the judges agree on can be calculated as a straightforward technique to assess inter-rater reliability.
- This is referred to as percent agreement, and it always falls between 0 and 1, with 0 denoting complete disagreement among raters and 1 denoting perfect agreement.
To know more about Inter-rater Reliability with the given link
brainly.com/question/14316125
#SPJ4
Answer:
Interest revenue = $7800*8%/360*60
Interest revenue = $104
Date Journal Entry Debit Credit
Cash $7,904
Notes Receivable $7,800
Interest Revenue $104
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
Answer:
the project's MIRR is 13.84 %
Explanation:
MODIFIED INTERNAL RATE OF RETURN (MIRR)
-It is the rate that causes the Present Value of the Terminal Value (Future Cash flows at the end of the Project) to equal Present Value of Cash outflows.
-MIRR assumes a reinvestment rate at the end of the project
The First Step is to Calculate the Terminal Value at end of year 3.
Terminal Value (FV) = Sum of (PV x (1 + r) ^ 3 - n)
= $450 x (1.09) ^ 2 + $450 x (1.09) ^ 1 + $450 x (1.09) ^ 0
= $534.65 + $490.50 + $450.00
= $1,475.15
The Next Step is to Calculate the MIRR using a Financial Calculator :
(-$1,000) CFj
0 CFj
0 CFj
$1,475.15 CFj
Shift IRR/Yr 13.84 %
Therefore, the project's MIRR is 13.84 %.
Answer:
The correct answer would be option C, When the price of a good decreases, sellers produce less of the good.
Explanation:
According to the law of supply, when the price of the product increases, the quantity supplied also increases.
This theory suggests that there is a direct relationship between the price of the product and the quantity supplied of the product. So when the price of a good decreases, sellers produce less of the good.