So... 4 folks, working for 8hours per day, do it in 15days
hmm alrite...so 4 folks working for 8hrs in 1 day, each one does 8, 4 of them, 4*8 = 32, so, they do 32 workhours every day, now for 15 days, that'd be 32*15, or 480
so, the whole job really takes 480 hours
now hmm let's see, the firm decides to increase the folks, but decrease the hours, so, 5 folks each working 6hours every day
how many workhours total? well 5*6 = 30
each is working 6hrs, 5 of them, so 30 workhours
how long will it take them if they only do 30 workhours everyday?
well the whole job is 480hours
Answer: bh=4×5=20b, h, equals, 4, times, 5, equals, 20 square units, so the area of the triangle is \dfrac 12 bh = \dfrac 12 \times 4 \times 5 = 10
2
1
bh=
2
1
×4×5=10start fraction, 1, divided by, 2, end fraction, b, h, equals, start fraction, 1, divided by, 2, end fraction, times, 4, times, 5, equals, 10
Step-by-step explanation:
The sum of two irrational numbers is only sometimes rational... So the answer is D.
Answer:
You did not include your graph, therefore I will explain in the step-by-step everything you should need to know.
Step-by-step explanation:
The standard slope formula is y=mx + b, where m = slope (rise/run) and b = the y intercept.
Using this knowledge, we know that this line has a slope of 5, or 5/1, which means that you will go up 5 and 1 to the right. Since there is no + b part, that means b = 0, so the line begins at 0,0. So, using this information, possible points include 0,0, 5,1, 10,2, 15,3, etc.
Answer:
-4
Step-by-step explanation: