Answer:
valence
Explanation:
Based on the information provided within the question it can be said that this scenario best illustrates the factor of valence. In the context of psychology this term refers to the attractiveness or adverseness of a situation, event or object. Which in this case would be Cynthia's one month leave, which depending on which perspective you take (Cynthia's or her Boss') it may either be viewed as good or bad.
Answer:
Task a:
The answer is $24,500.
Task b:
The answer is 17%
Explanation:
<h2>Task a:</h2><h3>What is the maximum amount of new capital that can be raised at the LOWEST component cost of EQUITY?</h3><h3>Solution:</h3>
We already know the following:
Projected net income = $21,000
Payout ratio = 30%
Retention ratio = 70%
Debt share = 40%
Equity share = 60%
Maximum amount of capital to be raised at the lowest component cost of equity = Projected net income ×
= $21,000 × 
= $24,500
<h3>Answer:</h3>
The maximum amount of new capital that can be raised at the lowest component of equity is $24,500.
<h2>Task b:</h2><h3>What is the component cost of equity by selling new common stock?</h3><h3>Solution:</h3>
k(e) (component cost of external equity) = [Dividend (D0)(1 + growth) / stock price(1 - flotation cost)] + growth
Formula:
k(e) =
+ 0.05
Where
Do = $2.00
G = 0.05
P = $21/88
= ($2.00(1 + 0.05) / $21.88(1-.20)) + 0.05
= ($2.10/$21.88(1-.20)) + 0.05
= ($2.10/$21.88(0.80) + 0.05
= 0.17 or 17%
<h3>Answer: </h3>
The component cost of equity by selling new common stock = 17%
Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.