Answer:
its B
Step-by-step explanation:
Its B
Actually I didn't see the (-5, -27), the answer would be -2.
Answer:
The WIP limit is 0.50 days.
Step-by-step explanation:
The Computation of WIP limits:
to begin with, it is required to compute the process and procedure efficiency which will be computed as follows:
Value Added Time = 12 days (arriving time)
Non-Value-Added Time = 12 days (departure time)
Efficiency = Value Added / (Value Added + Non-Value Added)
= 12 / (12+12)
= 12 / 24
= 0.50 or 50%
the most obligatory throughput time will be 0.25 days to realize the profits
WIP limit = Throughput time / Efficiency
= 0.25 / 50%
= 0.50 days.
The WIP limit is 0.50 days.
A) In Part 1 to part 2 the bus had its farthest distance. At part 2 the bus stayed steady time went by. Part 3 to 4 was decreasing distance. part 4 was constant. Then again at part 5 the distance was increasing
B)
1 - increasing
2 - constant
3 - decreasing
4 - constant
5 - increasing
C) Non-linear, because the graph has a curve, for it to be linear it must be a straight line.
Hope this Helps :)
Answer:
2.56
Step-by-step explanation:
The equation they dive u: d = 16t^2, so in the question they said what's the distance, d, if t = 0.4
So you just have to replace t with 0.4:
d = 16t^2
d = 16(0.4)^2
d = 16(0.16)
d = 2.56