Answer:
828.7 hours.
Step-by-step explanation:
To answer a question in which the total time has to be calculated of all the activities, first of all, all the times have to be converted to a single form. There are two types: decimals and fractions. Convert the fractions into decimals.
Department A = 202.50 hours.
Department B = 212 3⁄4 hours = 212.75 hours.
Department C = 198.25 hours.
Department D = 215 1⁄5 hours = 215.20 hours.
Therefore, the total number of hours spent on this project by all four departments. is the sum of all the above numbers. 202.50 hours + 212.75 hours + 198.25 hours + 215.20 hours = 828.7 hours.
Therefore, the total time is 828.7 hours!!!
The 4th option.
The values with no x or y attached are the y intercept
6x - 7y = 21
Subtract 6x from both sides
6x - 7y - 6x = 21 - 6x
-7y = 21 - 6x
Divide both sides by - 7
-7y/-7 = 21/-7 - 6x/-7
Y = -3 +6x/7
The why intercept, -3 is the same as the one in the question
Answer:
'A' is true; theoretically, 50% of the data items reside between the first and third quartiles (40 and 67.5)
Step-by-step explanation:
Range is 84-28 which is 56
Median is 51
1.5 x Interquartile Range (IQR) = 1.5(67.5-40) which equals 41.25
Q1 is 40
Q1 - IQR = -1.25
Low outliers are below -1.25 - 41.25; there are not data items below -42