Answer:
yes.
Step-by-step explanation:
sike.
Answer:
The answer to your question is 25 ft
Step-by-step explanation:
Data
height = 20 ft
leg = 15 ft
length of the line = ?
To solve this problem use the Pythagorean theorem.
Height = short leg = b
leg = long leg = a
length of the line = hypotenuse = c
- Substitution
c² = (20)² + (15)²
-Simplification
c² = 400 + 225
c² = 625
-Result
c = 
c = 25 ft
To make this new triangle I am going to pretend that the original triangle was at the points (4,4) (-4,4) and (0,8). So if this was dilated down by 1/2 then the triangles points would be (2,2) (-2,2) and (0,4). Then if it is reflected over the x-axis the new points would be (2,-2) (-2,-2) and (0,-4) and if it was translated left by 2 units then the points would be (0,-2) (-4,-2) and (-2, -4), then if the triangle was translated up by 4 units the points and the new triangle would be (0,2) (-4,2) and (-2,0). And that would be what the new triangle would be.
The triangle went from (4,4) (-4,4) and (0,8) to (0,2) (-4,2) and (-2,0).
Answer:
The value of x = 4
Step-by-step explanation:
In this question, we are asked to calculate the value of the angle x
Here the ray cuts the angle into half.
Since the total of the angle was 120, half of this would be 120/2 = 60
Now, it is this value of 60, that our new angle equals to
Mathematically;
3x + 48 = 60
3x = 60-48
3x = 12
x = 12/3
x = 4
Answer:
The triple constraint represents the three constraints or inputs which control the project's capacity to produce.
The three components are Budget, time, and scope.
The relationship between them is an interdependent or triangular shape.
Step-by-step explanation:
The triple constraint represents the three constraints or inputs which control the project's capacity to produce. Budget, Scope and Time.
- Budget - The budget describes the estimated cost of the project.
- Time: The time represents the deadline to complete the project.
- Scope: This is simply what needs to be provided.
These 3 components are dependent to each other.
For example, if time is restricted then scope and budget will be affected. similarly.
The relationship between the three is that one of the two other components must decrease while one component increases for the project to succeed as expected.